Share via Email | Share on Facebook| Share on Twitter

 

Construction Plans: 2013

What’s the problem?

Basically we have a leaking roof, even though the “roof” in this case is at ground level. The entire cathedral complex (the cathedral itself, with its office building, the Cathedral School for Boys, and the diocesan office building) has been built up over a period of almost a century. The Great Stairs, the outdoor labyrinth, the plaza and landscaping to the east and north of the cathedral were completed in 1995 as part of the close completion project. The occupied spaces under these areas include the Preschool/nursery, the Wilsey Conference Center, restrooms, storage areas and the parking garage. The waterproofing systems over these areas have failed in a number of locations and for a variety of reasons. 

What’s the solution?

We need to remove the surfaces and landscaping to expose the waterproofing membrane; then remove and replace the membrane; then install new concrete and masonry, and new landscaping. This work also requires bringing the facility up to current building code requirements for fire, safety and accessibility. This includes the spaces underneath the work area. While those spaces met all code requirements when they were built/remodeled, codes have changed since 2000. This requires adjustments to the cathedral elevator, improved handrails and lighting on the stairs, changes to some doors and improved signage.

What We Have Already DoneLabyrinth Planter Work and New Crypt Signage

In the summer of 2012, we got a start on waterproofing repairs and gained some good experience by working on the planters in front of the cathedral. We also used the time to make some of the necessary adjustments and improvements.

What would happen if we put off further repairs?

In the short term, there is the obvious issue of water damage to occupied spaces.  So far we have been controlling leaks by catching and diverting water above the ceilings of the restrooms, the Preschool and Wilsey rooms. That is increasingly difficult to do. In the longer term, the penetration of water into the steel-reinforced concrete structure results in the same kind of decay that required complete replacement of the roofs over the quire, north transept and Choir House.  The result of long-term leaking is complete replacement of a concrete structure.

Spring and summer of 2013:  When the big work will happen

  • First, the old elevator car in the cathedral has been replaced with a new car. 
  • From July through September 2013, the Great Stairs and the outdoor labyrinth will be removed. The failing waterproofing membrane will be removed and replaced. The stairs and labyrinth will then be replaced.
  • At the same time, all the doors along the east end of the cathedral will be lifted up and their leaking bearing boxes will be replaced.

The overall area affected by this project is shaded in light yellow in the diagram below. 
 

Obviously the 2013 work will cause major disruption, particularly when the stairs and outdoor labyrinth are replaced. The cathedral will remain open with all our usual activities occurring. Access will be via the California Street doors and both sets of doors leading from the plaza.

What will this cost and how will it be financed?

The total cost of the entire project is estimated at between $2.1 and $2.4 million.  We already have in hand one very generous gift from Sir William Fries II, who in 2008 gave the cathedral one million dollars to be used specifically for the Great Stairs project.  The rest of the money will be taken from funds from a prior bequest that was reserved specifically for building maintenance and restoration.

For more information, email Kathy Kirkpatrick, Canon Sacrist. 

 

 

© 2013 Grace Cathedral All Rights Reserved Grace Cathedral
1100 California St
San Francisco, CA 94108
415-749-6300

Website Design and Content Management by 1250 Media